Mark Kneipp Amadeus Basin 2D Seismic Case Study Project Summary 2D Seismic Survey in the Amadeus Basin, Northern Territory. 20km main line with 5 parallel ghost lines + 2 receiver grids 4,758 Receiver Points, 1,592 Source Points. Timeframe - Planni... 22 Oct 2024 Our blog
Mark Kneipp Bowen Basin 2D Seismic Case Study Project summary 124km 2D Seismic Survey in the Bowen Basin, Queensland. 12,397 Receiver Points, 12,397 Source Points. Timeframe - Planning 160 days, Delivery 18 days. Seismic contractor - Terrex Se... 22 Oct 2024 Our blog